Cob Workshop Stone Foundation

In anticipation of our upcoming cob workshops to build Colin’s woodworking shop, we have been busy setting up the foundation and floor of the building.  The spot where we are building is tucked up against the bedrock slope that slants down and somewhat divides our land into upper and lower sections, the upper section being where we have just completed the first half of our strawbale house which will eventually be extended down the rock slope.  The workshop is situated off to the side of this slope and as close to the side line of the property as we can go.

In early July we had an excavator come and dig out 2 foot wide trenches that would hold 18 inch deep concrete footing walls with drain rock along the outside.  Colin built forms down the middle of the trench, using the clay walls as the forms on the inside of the trench and leaving the outer side empty for filling with drain rock.  We dug a connecting trench and placed a drain pipe that went down hill towards the garden.  Colin added a small grid of rebar in the bottom of the trench and then called in the cement truck to pour the footings.  He added stakes of rebar throughout the wall to tie together later after the stonework was done, as was requested by our engineer for seismic strengthening of the stone and concrete.  He also dug footings for the skylight posts and placed saddles after the concrete pour.  The concrete footing wall came up to the height of the clay grade, and provided a strong ledge onto which the excavator would place many of the massive stones that exist on our property.

So by mid July, we had the excavator back and picking huge stones from our pile that Colin directed into the spaces between the rebar stakes, trying to place them in such a way so that he could fill in between them manually with smaller stones.  He mixed and shoveled concrete as each stone was set, and adjusted the placement so that the outside edge was either flat or sloping downwards for water run off.  In the pile, he found two huge flat stones that were placed at the front double door entrance to the shop.  Then he spent the next few days picking smaller rocks and cementing them in the spaces, creating a two foot wide, irregularly stacked stone ledge two feet high onto which the cob wall will be stacked, keying in to the varying height of the stones for extra solidity between the cob and the stone wall.

A large pile of clay left from the digging of the trenches will be used as part of the clay we need for mixing the cob, and a large pile of local pit run sand is being delivered in the next few days.  Bales of straw will be picked up from the Saanich Peninsula, and a huge tarp has been strung up to protect the space from the heat of the sun as well as the unseasonal threats of rain we have been getting.  The food menu for the workshop participants is being finalized, and we have even had a friend come by to film the construction of the foundation with the idea of making a small movie of the cobbing workshops and the process of building this small natural building.

We are off in a few days to our annual family music camp, so getting as much done and in place now will help us feel more prepared when we arrive home and have cobbers showing up four days later!  We are very excited about hosting this learning opportunity, and creating a beautiful space for Colin to work in.  We are still accepting people to join us- see the previous post Cob Workshop Approved for details of the cobbing workshops in August.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: